Construction Contracts Completed On-Time

This core measure is the percent of FDOT highway and bridge construction contracts that are completed within 20% of the original schedule. Of the 314 construction contracts completed in fiscal year 2019/20, 86% were completed within 20% of the original schedule estimate, which surpassed FDOT’s 80% goal.

By completing contracts on time, FDOT and its contractors save time and money for freight shippers and the industries that depend on them, as well as for other road users. Completing contracts on time also helps reduce the extent of time delays and cost associated with travel through construction work zones. This reflects FDOT’s emphasis on responding to customer needs and priorities.